Whitby Water Supply Plant
Pump Station Relocation

Client:  Jeviso Construction Corporation, Vaughan ON​

​

Contract Type / Kehoe Role: Subcontract Agreement / Marine Subcontractor

​

Project Summary:

​

General Description of the work included:

​

  • Interior cleaning of the existing intake pipe (CPP) in Lake Ontario and intake pipe from surge chamber/intake chamber to intake well, as required to perform work.

  • New high density polyethylene (HDPE) DR11 raw water sample lines and chlorination lines including all valves, fittings, connections, fasteners, ballast cable and all related appurtenances.

  • New 75 mm schedule 80 PVC Diffuser and related accessories.

  • Submittals including work plans, health and safety plans, environmental protection plans, shop drawings, Operating, Maintenance Manuals.

  • Mechanical connection and commissioning the system.

​

New Raw Water and Chlorine Lines Work included:

​

  • Removal of existing chlorine solution and raw water sampling lines, diffuser and associated appurtenances in the plant intake (intake crib to respective pumps connections at the Whitby WSP).

  • Remotely operated vehicle (ROV) inspections of the intake, as described herein.

  • Cleaning of intake crib and intake structure down the intake shaft elbow (removal of mussel and silt accumulation along all surface walls, ceiling and floor of shaft structure).

  • Fabrication, installation, testing and commissioning of new chlorine solution and raw water sampling pipe bundles and diffusers in the plant intake at the Whitby WSP.

  • Secure and pay for the cost of additional required permits.

 